1. The aim of the project is to complete the basic motorway D1, improve conditions for international and national traffic and increase fluidity, capacity, speed and road safety. After the completion of the construction of the section D1 in the length of 7.87 km, conditions will be created for a substantial reduction of traffic on road I/68 and road I/18 (deviation of transit freight and passenger traffic from the city of Prešov).2. The activities of the project focus on the construction of motorways and expressways, including feeders (TEN-T CORE), with the aim of removing key bottlenecks on t…

EU budget
€278.3M
Total project cost
€327.4M
Period
2017-06-01 → 2022-12-01
Thematic objective
TO07Sustainable transport and network infrastructure

About the Sustainable transport and network infrastructure objective

Thematic Objective 7 funds sustainable transport and network infrastructure: TEN-T core-network completion, rail electrification, urban mobility, ports and inland-waterway upgrades.

Co-funding: the EU contributes €278.3M toward a total project cost of €327.4M — a co-funding rate of 85%, with the remainder covered by national, regional or private sources.

Kohesio is the European Commission's open-data platform for projects co-financed by the European Regional Development Fund, the European Social Fund Plus, the Cohesion Fund and the Just Transition Fund. It draws on lists of beneficiaries published by national managing authorities and harmonises them into a single EU-wide view.

Full project record on Kohesio — partners, deliverables, location map, related funding decisions.

Open on kohesio.ec.europa.eu →

Frequently asked questions

What is the EU budget for this project?
The EU contributes €278.3M toward a total project cost of €327.4M, a co-funding rate of 85%.
Which fund or thematic objective does it belong to?
This project falls under EU Cohesion Policy thematic objective TO07 — Sustainable transport and network infrastructure — financed through the European Structural and Investment Funds.
Which country is the project located in?
The project is located in SK.
What is the project period?
The project runs from 2017-06-01 to 2022-12-01.
Where can I find the full project record?
The complete project record — beneficiary, location and related funding decisions — is published on Kohesio, the European Commission's open-data platform, under reference Q3102572.