Modernisation of the Oder Weirs on the section of the Management Board of RZGW Gliwice – Opolskie Voivodeship (Stage II)

The project involves the modernisation of three weirs located on the Oder: Tight, Well, Groszowice to adapt the Oder to the third class of the waterway. The investment will contribute to improving the operating conditions of the facilities in terms of their failure-freeness, and thus the efficiency of controlling the process of passing water through the analysed weirs, which, in the current technical condition, present many operational problems resulting from frequent failures, which result in the impossibility of properly manoeuvring closures and maintaining an appropriate level of navigable…

EU budget
€48.7M
Total project cost
€57.3M
Period
2017-02-01 → 2023-09-30
Thematic objective
TO07Sustainable transport and network infrastructure

About the Sustainable transport and network infrastructure objective

Thematic Objective 7 funds sustainable transport and network infrastructure: TEN-T core-network completion, rail electrification, urban mobility, ports and inland-waterway upgrades.

Co-funding: the EU contributes €48.7M toward a total project cost of €57.3M — a co-funding rate of 85%, with the remainder covered by national, regional or private sources.

Kohesio is the European Commission's open-data platform for projects co-financed by the European Regional Development Fund, the European Social Fund Plus, the Cohesion Fund and the Just Transition Fund. It draws on lists of beneficiaries published by national managing authorities and harmonises them into a single EU-wide view.

Full project record on Kohesio — partners, deliverables, location map, related funding decisions.

Open on kohesio.ec.europa.eu →

Frequently asked questions

What is the EU budget for this project?
The EU contributes €48.7M toward a total project cost of €57.3M, a co-funding rate of 85%.
Which fund or thematic objective does it belong to?
This project falls under EU Cohesion Policy thematic objective TO07 — Sustainable transport and network infrastructure — financed through the European Structural and Investment Funds.
Which country is the project located in?
The project is located in PL.
What is the project period?
The project runs from 2017-02-01 to 2023-09-30.
Where can I find the full project record?
The complete project record — beneficiary, location and related funding decisions — is published on Kohesio, the European Commission's open-data platform, under reference Q2693010.