KOHESIO · Q3107599 · SK

Reconstruction of road and bridges II/591 district. DT and II/585 district LC – Stage I

The project is aimed at improving the construction and technical condition of roads II/585 and II/591 and increasing the safety parameters of the sections in the districts of Lučenec and Detva. The expected length of reconstruction of the road II/585 is 4,116 km, with reconstruction and renewal of 3 bridges and the expected length of reconstruction of the road II/591 is 12.853 km, with reconstruction and renewal of 5 bridge buildings. The aim and purpose is to ensure the continuity and safety of transport, the reduction of the negative impact of road transport on the environment of the countr…

EU budget
€4.9M
Total project cost
€5.8M
Period
2021-01-08 → 2023-01-07
Thematic objective
TO07Sustainable transport and network infrastructure

About the Sustainable transport and network infrastructure objective

Thematic Objective 7 funds sustainable transport and network infrastructure: TEN-T core-network completion, rail electrification, urban mobility, ports and inland-waterway upgrades.

Co-funding: the EU contributes €4.9M toward a total project cost of €5.8M — a co-funding rate of 85%, with the remainder covered by national, regional or private sources.

Kohesio is the European Commission's open-data platform for projects co-financed by the European Regional Development Fund, the European Social Fund Plus, the Cohesion Fund and the Just Transition Fund. It draws on lists of beneficiaries published by national managing authorities and harmonises them into a single EU-wide view.

Full project record on Kohesio — partners, deliverables, location map, related funding decisions.

Open on kohesio.ec.europa.eu →

Frequently asked questions

What is the EU budget for this project?
The EU contributes €4.9M toward a total project cost of €5.8M, a co-funding rate of 85%.
Which fund or thematic objective does it belong to?
This project falls under EU Cohesion Policy thematic objective TO07 — Sustainable transport and network infrastructure — financed through the European Structural and Investment Funds.
Which country is the project located in?
The project is located in SK.
What is the project period?
The project runs from 2021-01-08 to 2023-01-07.
Where can I find the full project record?
The complete project record — beneficiary, location and related funding decisions — is published on Kohesio, the European Commission's open-data platform, under reference Q3107599.