KOHESIO · Q4430500 · PL

Construction of the northern ring road of Krakow within S52

The main part of the project is the construction of the north bypass of Krakow within the S52 length. 11.48 km. The beginning of the construction was taken in km 2 + 650.70 in the Great Village in the district of Kraków, where the planned road connects with the existing section of the road express. S52 in the existing “Modlnica” junction and runs in a new trail bypassing the surrounding dense buildings. As part of the project, the “Modlnica” junction is extended with additional traffic relations and OUD, hence works will also be carried out on the existing section S52 from km 2+ 134.50 to km …

EU budget
€189.5M
Total project cost
€223.0M
Period
2014-01-01 → 2023-12-31
Thematic objective
TO07Sustainable transport and network infrastructure

About the Sustainable transport and network infrastructure objective

Thematic Objective 7 funds sustainable transport and network infrastructure: TEN-T core-network completion, rail electrification, urban mobility, ports and inland-waterway upgrades.

Co-funding: the EU contributes €189.5M toward a total project cost of €223.0M — a co-funding rate of 85%, with the remainder covered by national, regional or private sources.

Kohesio is the European Commission's open-data platform for projects co-financed by the European Regional Development Fund, the European Social Fund Plus, the Cohesion Fund and the Just Transition Fund. It draws on lists of beneficiaries published by national managing authorities and harmonises them into a single EU-wide view.

Full project record on Kohesio — partners, deliverables, location map, related funding decisions.

Open on kohesio.ec.europa.eu →

Frequently asked questions

What is the EU budget for this project?
The EU contributes €189.5M toward a total project cost of €223.0M, a co-funding rate of 85%.
Which fund or thematic objective does it belong to?
This project falls under EU Cohesion Policy thematic objective TO07 — Sustainable transport and network infrastructure — financed through the European Structural and Investment Funds.
Which country is the project located in?
The project is located in PL.
What is the project period?
The project runs from 2014-01-01 to 2023-12-31.
Where can I find the full project record?
The complete project record — beneficiary, location and related funding decisions — is published on Kohesio, the European Commission's open-data platform, under reference Q4430500.