KOHESIO · Q4583925 · CZ

Road I/27 Šlovice — Přeštice, relay

The subject of the project is the construction of a transfer of road I/27 in the total length of the main route 6.095 km mainly in category S 21,5/110, which is dealt with as the western bypass of the municipality of Horní Lukavice. The implementation of the project will lead to transit traffic away from the municipality and reduce the burden on the population through noise and exhalations. It will also increase traffic flow on road I/27, reduce driving time and improve road safety in the municipality of Horní Lukavice, including pedestrian safety.

EU budget
€43.1M
Total project cost
€50.7M
Period
2020-04-29 → —
Thematic objective
TO07Sustainable transport and network infrastructure

About the Sustainable transport and network infrastructure objective

Thematic Objective 7 funds sustainable transport and network infrastructure: TEN-T core-network completion, rail electrification, urban mobility, ports and inland-waterway upgrades.

Co-funding: the EU contributes €43.1M toward a total project cost of €50.7M — a co-funding rate of 85%, with the remainder covered by national, regional or private sources.

Kohesio is the European Commission's open-data platform for projects co-financed by the European Regional Development Fund, the European Social Fund Plus, the Cohesion Fund and the Just Transition Fund. It draws on lists of beneficiaries published by national managing authorities and harmonises them into a single EU-wide view.

Full project record on Kohesio — partners, deliverables, location map, related funding decisions.

Open on kohesio.ec.europa.eu →

Frequently asked questions

What is the EU budget for this project?
The EU contributes €43.1M toward a total project cost of €50.7M, a co-funding rate of 85%.
Which fund or thematic objective does it belong to?
This project falls under EU Cohesion Policy thematic objective TO07 — Sustainable transport and network infrastructure — financed through the European Structural and Investment Funds.
Which country is the project located in?
The project is located in CZ.
What is the project period?
The project runs from 2020-04-29 to —.
Where can I find the full project record?
The complete project record — beneficiary, location and related funding decisions — is published on Kohesio, the European Commission's open-data platform, under reference Q4583925.