KOHESIO · Q4609540 · RO

Works at C.F. Fetești and Ciulnita Stations, on the Bucharest — Constanta railway line

The overall objective of the project is set in direct correlation with Priority Axis 1 — Improving mobility by developing the TEN-T network and metro transport; Specific objective 1.2 — Increasing mobility on the TEN-T core rail network. The rehabilitation project for the works at Fetești and Ciulnita stations is an integral part of the Master General Transport Plan of Romania, a strategic document for the development of the national transport infrastructure, approved by the Romanian Government by Decision no. 666/2016. The Bucharest-Constanţa railway line is an important line of the Romanian…

EU budget
€56.0M
Total project cost
€65.9M
Period
2019-07-15 → 2023-12-31
Thematic objective
TO07Sustainable transport and network infrastructure

About the Sustainable transport and network infrastructure objective

Thematic Objective 7 funds sustainable transport and network infrastructure: TEN-T core-network completion, rail electrification, urban mobility, ports and inland-waterway upgrades.

Co-funding: the EU contributes €56.0M toward a total project cost of €65.9M — a co-funding rate of 85%, with the remainder covered by national, regional or private sources.

Kohesio is the European Commission's open-data platform for projects co-financed by the European Regional Development Fund, the European Social Fund Plus, the Cohesion Fund and the Just Transition Fund. It draws on lists of beneficiaries published by national managing authorities and harmonises them into a single EU-wide view.

Full project record on Kohesio — partners, deliverables, location map, related funding decisions.

Open on kohesio.ec.europa.eu →

Frequently asked questions

What is the EU budget for this project?
The EU contributes €56.0M toward a total project cost of €65.9M, a co-funding rate of 85%.
Which fund or thematic objective does it belong to?
This project falls under EU Cohesion Policy thematic objective TO07 — Sustainable transport and network infrastructure — financed through the European Structural and Investment Funds.
Which country is the project located in?
The project is located in RO.
What is the project period?
The project runs from 2019-07-15 to 2023-12-31.
Where can I find the full project record?
The complete project record — beneficiary, location and related funding decisions — is published on Kohesio, the European Commission's open-data platform, under reference Q4609540.