KACELLE Demonstrating Industrial Scale Second Generation Bioethanol Production - KAlundborg CELLulosic Ethanol plant

Coordinator: DONG ENERGY WIND POWER HOLDING AS (DK)

The aim of this project is to bring the patented Inbicon Core technology for 2nd generation bio-ethanol production from a pre-commercial to a full commercial level, making the technology available in the market and attractive to investors in 4 – 5 years. The technology was developed in steps (also partly EU funded) and now a 4 t/hr biomass to ethanol plant is being built in Kalundborg in Denmark. The plant will be in operation in the fall of 2009 and will produce 5 million litres of ethanol annually. More than 10 years of development has brought about a robust process capable of producing sub…

EU contribution
€9.1M
Total cost
€16.2M
Period
2009-08-01 → 2013-07-31
Framework
Seventh Framework Programme (2007–2013)
Funding scheme
CP
Status
CLOSED

About Seventh Framework Programme (2007–2013)

The Seventh Framework Programme (FP7) ran from 2007 to 2013 and was the EU's main research-funding instrument of that period. It mobilised roughly €50 billion across cooperation projects, ERC frontier grants, Marie Curie fellowships, capacity-building actions and Euratom research. FP7 closed to new calls in 2013 but its projects continued for years after under their original grant agreements.

Co-funding: the European Union contributes €9.1M toward a total project budget of €16.2M — a funding rate of 56%, with the remainder covered by the consortium partners. The project runs over approximately 4 years from 2009-08-01 to 2013-07-31.

Full record on CORDIS — partners, deliverables, publications, news.

Open on cordis.europa.eu →

Frequently asked questions

Who funds this research project?
This project is funded by the European Union through the Seventh Framework Programme (2007–2013) programme, under the CP funding scheme.
What is the EU contribution?
The European Commission contributes €9.1M toward a total project budget of €16.2M.
Which EU programme funds it?
The project is funded under Seventh Framework Programme (2007–2013).
Who coordinates the project?
The project is coordinated by DONG ENERGY WIND POWER HOLDING AS (DK).
What is the project timeline?
The project runs from 2009-08-01 to 2013-07-31 — approximately 4 years.