KOHESIO · Q3810757 · LT

Reconstruction of Lentvaris level crossing

The reconstructed level crossing is located in the city centre of Lentvaris and divides the city into two parts, and the crossing in the centre through five railway tracks is the only place through which car vehicles, together with pedestrians and cyclists, can enter from the northern part of the city to the south and vice versa._x000D_The project is newly equipped with a cross-section of different levels — a car tunnel under the railway with a common pedestrian and cycling path; pedestrian — cyclist overpasses (2 pcs.), one-level intersections — small circular (Geležinkel and Fabriko str.) a…

EU budget
€10.6M
Total project cost
€17.0M
Period
2020-09-15 → 2022-03-31
Thematic objective
TO07Sustainable transport and network infrastructure

About the Sustainable transport and network infrastructure objective

Thematic Objective 7 funds sustainable transport and network infrastructure: TEN-T core-network completion, rail electrification, urban mobility, ports and inland-waterway upgrades.

Co-funding: the EU contributes €10.6M toward a total project cost of €17.0M — a co-funding rate of 62%, with the remainder covered by national, regional or private sources.

Kohesio is the European Commission's open-data platform for projects co-financed by the European Regional Development Fund, the European Social Fund Plus, the Cohesion Fund and the Just Transition Fund. It draws on lists of beneficiaries published by national managing authorities and harmonises them into a single EU-wide view.

Full project record on Kohesio — partners, deliverables, location map, related funding decisions.

Open on kohesio.ec.europa.eu →

Frequently asked questions

What is the EU budget for this project?
The EU contributes €10.6M toward a total project cost of €17.0M, a co-funding rate of 62%.
Which fund or thematic objective does it belong to?
This project falls under EU Cohesion Policy thematic objective TO07 — Sustainable transport and network infrastructure — financed through the European Structural and Investment Funds.
Which country is the project located in?
The project is located in LT.
What is the project period?
The project runs from 2020-09-15 to 2022-03-31.
Where can I find the full project record?
The complete project record — beneficiary, location and related funding decisions — is published on Kohesio, the European Commission's open-data platform, under reference Q3810757.