KOHESIO · Q3942941 · HU

On the section of main road No 55 between Mórahalom bypass and the county boundary, reinforcement of the pavement to 115 kN axle load and completion of the construction work of a bicycle road parallel to the main road

The section between the Mórahalom bypass and the county boundary planned on main road No 55 is to strengthen the pavement for 115 kN axle loads and to build a parallel cycle path. The project will carry out a feasibility study in accordance with the conditions set out in the IKOP Guide, and a declaration on compliance with the Water Framework Directive and on climate risk will be procured. The CBA analysis is also carried out for continuous review. The existing MT and CBA will be updated. Main technical tasks of the project: 15.7 km long 2x1 lane section 115 kN pavement reinforcement, upgradi…

EU budget
€15.5M
Total project cost
€23.7M
Period
2016-09-30 → 2018-07-15
Thematic objective
TO07Sustainable transport and network infrastructure

About the Sustainable transport and network infrastructure objective

Thematic Objective 7 funds sustainable transport and network infrastructure: TEN-T core-network completion, rail electrification, urban mobility, ports and inland-waterway upgrades.

Co-funding: the EU contributes €15.5M toward a total project cost of €23.7M — a co-funding rate of 65%, with the remainder covered by national, regional or private sources.

Kohesio is the European Commission's open-data platform for projects co-financed by the European Regional Development Fund, the European Social Fund Plus, the Cohesion Fund and the Just Transition Fund. It draws on lists of beneficiaries published by national managing authorities and harmonises them into a single EU-wide view.

Full project record on Kohesio — partners, deliverables, location map, related funding decisions.

Open on kohesio.ec.europa.eu →

Frequently asked questions

What is the EU budget for this project?
The EU contributes €15.5M toward a total project cost of €23.7M, a co-funding rate of 65%.
Which fund or thematic objective does it belong to?
This project falls under EU Cohesion Policy thematic objective TO07 — Sustainable transport and network infrastructure — financed through the European Structural and Investment Funds.
Which country is the project located in?
The project is located in HU.
What is the project period?
The project runs from 2016-09-30 to 2018-07-15.
Where can I find the full project record?
The complete project record — beneficiary, location and related funding decisions — is published on Kohesio, the European Commission's open-data platform, under reference Q3942941.