KOHESIO · Q3943245 · HU
Construction of the flood protection system of Felső-Tisza, Tisza-Túr reservoir
The construction of the Tisza-Túr reservoir affects an area of ~17 km² on the NW side of main road 491, where, assuming a storage level of 118,0 mBf, around 45 million m³ of water can be stored in the area. It is predominantly the most significant in one of the most critical sections of the Upper Tisza (the narrowing between Tisabeck-Tiszaújlak, which is similar to the Tivadari constriction). It is also justified by the fact that the flooding of the river Túr, built by regulation of the Tisza, can have such a bulging effect, resulting in 3-4 m flooding in the settlements of Tiszacsécse, Tisza…
About the Climate change adaptation, risk prevention objective
Thematic Objective 5 supports climate-change adaptation and risk prevention: flood defences, wildfire prevention, drought-management infrastructure, civil-protection systems, and ecosystem-based adaptation.
Co-funding: the EU contributes €86.3M toward a total project cost of €101.5M — a co-funding rate of 85%, with the remainder covered by national, regional or private sources.
Kohesio is the European Commission's open-data platform for projects co-financed by the European Regional Development Fund, the European Social Fund Plus, the Cohesion Fund and the Just Transition Fund. It draws on lists of beneficiaries published by national managing authorities and harmonises them into a single EU-wide view.
Full project record on Kohesio — partners, deliverables, location map, related funding decisions.
Open on kohesio.ec.europa.eu →More projects in HU
see all →- Modernisation of the Püspökladány-Debrecen railway line, preparation of the partial reconstruction of Debrecen station and the construction of an ETCS train control system on the Szajol-Debrecen railway lineQ3942980 · €258.9M
- M35 motorway No. 4 — Main road 481, main road 481 — Berettyóújfalu section and implementation of main road 481Q3942932 · €169.0M
- M86 express road Szeleste — Csorna section II implementation Hegyfalu — Csorna section between 105+ 800-139+ 165 kmQ3942930 · €148.3M
- Development of digital competenceQ3898383 · €116.1M
- Püspökladány — Bihor Cross bottleneck replacement and electrificationQ3942979 · €115.0M
- GSM-R deployment phase 2 on the Hungarian TEN-T rail comprehensive networkQ3942992 · €68.7M
Same objective, other countries
see all →- Protection against flooding of the Klodzka Basin with particular emphasis on the protection of the city of KłodzkaQ85090 · PL · €88.7M
- Modernisation of the beautiful slide from Račinovac to Nova GradiškaQ2734052 · HR · €41.7M
- Comprehensive project for adaptation of forests and forestry to climate change – low retention and prevention of water erosion in lowland areasQ85047 · PL · €40.8M
- Construction and reconstruction of rainwater drainage and adaptation of the rainwater drainage network to climate change in the city of BydgoszczQ85104 · PL · €34.4M
- Upgrading of the Republic of Croatia’s fire-brigadeQ2734051 · HR · €28.9M
- Protection against flooding of the city of SłubiceQ85078 · PL · €26.8M
Frequently asked questions
- What is the EU budget for this project?
- The EU contributes €86.3M toward a total project cost of €101.5M, a co-funding rate of 85%.
- Which fund or thematic objective does it belong to?
- This project falls under EU Cohesion Policy thematic objective TO05 — Climate change adaptation, risk prevention — financed through the European Structural and Investment Funds.
- Which country is the project located in?
- The project is located in HU.
- What is the project period?
- The project runs from 2018-10-01 to 2023-09-30.