Extension of provincial road No 221 from Janków to the Kościerzyna Bypass - Section D from Nowa Karczma to Kościerzyna
As part of the task, 11.95 km of provincial road No. 221 and intersections located on this section of road will be extended. The investment starts in Nowa Karczma at km 39+850 and ends at km 51+800 in front of the junction with the Bypass in Kościerzyna. In addition, the areas of intersections of district and municipal roads with the provincial road, as well as a number of elements of the existing technical infrastructure, will be subject to construction and reconstruction. The aim of the extension of the planned section is to adapt the technical parameters of the existing road to those of th…
Co-funding: the EU contributes €28.9M toward a total project cost of €40.1M — a co-funding rate of 72%, with the remainder covered by national, regional or private sources.
Kohesio is the European Commission's open-data platform for projects co-financed by the European Regional Development Fund, the European Social Fund Plus, the Cohesion Fund and the Just Transition Fund. It draws on lists of beneficiaries published by national managing authorities and harmonises them into a single EU-wide view.
Full project record on Kohesio — partners, deliverables, location map, related funding decisions.
Open on kohesio.ec.europa.eu →More projects in PL
see all →- SME Liquidity Loan Fund – FPWP OP IRQ2687767 · €684.0M
- Construction of the A1 motorway, the end of the Czestochowa – Tuszyn ring roadQ2693001 · €407.6M
- Construction of the S6 section. Słupsk – DK6 (Bożepole Wielkie)Q7374976 · €345.0M
- RES developmentQ7374888 · €336.0M
- Construction of the S7 road, sec. Płońsk (S10) – GarlicQ7374962 · €299.2M
- Construction of ERTMS/GSM-R system infrastructure on PKP Polskie Linie Kolejowe S.A. railway lines within ERTMS NPWQ85996 · €266.3M
Same objective, other countries
see all →- Highway Sibiu - FagarasQ7416222 · RO · €561.7M
- Ruse – Veliko Tarnovo Motorway from km 0+400 to km 76+040Q7445163 · BG · €445.6M
- Integrated infrastructure for the orbital area of Bucharest - Phase IIQ7416799 · RO · €335.8M
- Acquisition of new rolling stock - 37 interregional multiple electric units (RE-IR)Q7416995 · RO · €242.7M
- BRONZE DETENTION AND SEARCH DETENTIONQ7481776 · GR · €196.4M
- Electrification of the railway on the Tallinn-Tartu and Tapa-Narva lines (phase 1)Q7427143 · EE · €192.3M
Frequently asked questions
- What is the EU budget for this project?
- The EU contributes €28.9M toward a total project cost of €40.1M, a co-funding rate of 72%.
- Which fund or thematic objective does it belong to?
- This project falls under EU Cohesion Policy thematic objective PO03 — PO03 — financed through the European Structural and Investment Funds.
- Which country is the project located in?
- The project is located in PL.
- What is the project period?
- The project runs from 2024-05-27 to 2026-06-30.
- Where can I find the full project record?
- The complete project record — beneficiary, location and related funding decisions — is published on Kohesio, the European Commission's open-data platform, under reference Q7376498.