KOHESIO · Q3067954 · EE

Reconstruction of the Väo-Jüri section of Tallinn ring road No 11 (E265)

The road complying with the road requirements shall be constructed at I kl by adding the directions to the left of the existing road and from Pk 14+ 00 to the right. The Veneküla junction tunnel, viaducts of Väo and Lagedi railways, 2 Pirita-Upper Canal bridges, Karla and Hellfield viaducts will be built. 4 different intersections (with tunnels) will be upgraded. A new section will be built to connect Tallinn-Laged and Lagedi-Aruküla-Pening highways and light traffic routes to the Russian Village tunnel, to the viaducts of Karla and Hellfield and to connect Pildiküla and Jüri.

EU budget
€36.6M
Total project cost
€43.1M
Period
2015-06-01 → 2021-12-31
Thematic objective
TO07Sustainable transport and network infrastructure

About the Sustainable transport and network infrastructure objective

Thematic Objective 7 funds sustainable transport and network infrastructure: TEN-T core-network completion, rail electrification, urban mobility, ports and inland-waterway upgrades.

Co-funding: the EU contributes €36.6M toward a total project cost of €43.1M — a co-funding rate of 85%, with the remainder covered by national, regional or private sources.

Kohesio is the European Commission's open-data platform for projects co-financed by the European Regional Development Fund, the European Social Fund Plus, the Cohesion Fund and the Just Transition Fund. It draws on lists of beneficiaries published by national managing authorities and harmonises them into a single EU-wide view.

Full project record on Kohesio — partners, deliverables, location map, related funding decisions.

Open on kohesio.ec.europa.eu →

Frequently asked questions

What is the EU budget for this project?
The EU contributes €36.6M toward a total project cost of €43.1M, a co-funding rate of 85%.
Which fund or thematic objective does it belong to?
This project falls under EU Cohesion Policy thematic objective TO07 — Sustainable transport and network infrastructure — financed through the European Structural and Investment Funds.
Which country is the project located in?
The project is located in EE.
What is the project period?
The project runs from 2015-06-01 to 2021-12-31.
Where can I find the full project record?
The complete project record — beneficiary, location and related funding decisions — is published on Kohesio, the European Commission's open-data platform, under reference Q3067954.