KOHESIO · Q3832249 · BG

Construction of WSS infrastructure for the separate territory of “WSS” Ltd. Silistra

The project proposal provides for the implementation of integrated investment measures on the territory served by WSS OOD, Silistra. The investments are aimed at achieving compliance of agglomerations above 10 000 p.e., namely the agglomeration of Silistra, with the requirements of Directive 91/271/EEC. The investments envisaged are also aimed at increasing the efficiency of the water supply networks, reducing water losses as well as achieving water supply security and compliance with Directive 98/83/EC for the two agglomerations with more than 10 000 inhabitants, Silistra and Tutrakan. The e…

EU budget
€25.8M
Total project cost
€33.7M
Period
2019-09-05 → 2024-03-05
Thematic objective
TO06Environment and resource efficiency

About the Environment and resource efficiency objective

Thematic Objective 6 finances environment and resource efficiency — water and waste management, biodiversity protection, contaminated-site remediation, air quality, and the circular economy.

Co-funding: the EU contributes €25.8M toward a total project cost of €33.7M — a co-funding rate of 76%, with the remainder covered by national, regional or private sources.

Kohesio is the European Commission's open-data platform for projects co-financed by the European Regional Development Fund, the European Social Fund Plus, the Cohesion Fund and the Just Transition Fund. It draws on lists of beneficiaries published by national managing authorities and harmonises them into a single EU-wide view.

Full project record on Kohesio — partners, deliverables, location map, related funding decisions.

Open on kohesio.ec.europa.eu →

Frequently asked questions

What is the EU budget for this project?
The EU contributes €25.8M toward a total project cost of €33.7M, a co-funding rate of 76%.
Which fund or thematic objective does it belong to?
This project falls under EU Cohesion Policy thematic objective TO06 — Environment and resource efficiency — financed through the European Structural and Investment Funds.
Which country is the project located in?
The project is located in BG.
What is the project period?
The project runs from 2019-09-05 to 2024-03-05.
Where can I find the full project record?
The complete project record — beneficiary, location and related funding decisions — is published on Kohesio, the European Commission's open-data platform, under reference Q3832249.