Lot 1 “Road II-57 St. Zagora-Radnevo-Road II-55 from km 0+ 250 to km 11+ 075 and from km 12+ 460 to km 40+ 554, with a total length of 38.919 km, districts of Sliven and St. Zagora”

The main objective of this project proposal is to rehabilitate road II-57 Stara Zagora-Radnevo-road II-55 from km 0+ 250 to km 11+ 075 and from km 12+ 460 to km 40+ 554, improving and modernising the technical and operational characteristics of the section and achieving uniformity of the road surface. The implementation of the project will lead to: increasing the mobility of the population, increasing investment in the region, creating new jobs, improving the state of the environment by reducing the emission of harmful greenhouse gas emissions and allowing more choice to health and education …

EU budget
€10.7M
Total project cost
€12.5M
Period
2016-05-09 → 2020-08-21
Thematic objective
TO07Sustainable transport and network infrastructure

About the Sustainable transport and network infrastructure objective

Thematic Objective 7 funds sustainable transport and network infrastructure: TEN-T core-network completion, rail electrification, urban mobility, ports and inland-waterway upgrades.

Co-funding: the EU contributes €10.7M toward a total project cost of €12.5M — a co-funding rate of 85%, with the remainder covered by national, regional or private sources.

Kohesio is the European Commission's open-data platform for projects co-financed by the European Regional Development Fund, the European Social Fund Plus, the Cohesion Fund and the Just Transition Fund. It draws on lists of beneficiaries published by national managing authorities and harmonises them into a single EU-wide view.

Full project record on Kohesio — partners, deliverables, location map, related funding decisions.

Open on kohesio.ec.europa.eu →

Frequently asked questions

What is the EU budget for this project?
The EU contributes €10.7M toward a total project cost of €12.5M, a co-funding rate of 85%.
Which fund or thematic objective does it belong to?
This project falls under EU Cohesion Policy thematic objective TO07 — Sustainable transport and network infrastructure — financed through the European Structural and Investment Funds.
Which country is the project located in?
The project is located in BG.
What is the project period?
The project runs from 2016-05-09 to 2020-08-21.
Where can I find the full project record?
The complete project record — beneficiary, location and related funding decisions — is published on Kohesio, the European Commission's open-data platform, under reference Q3835728.