KOHESIO · Q3835746 · BG

Lot 26 “Road III-507 Kardzhali-Monastery from km 0+ 055 to km 26+ 109, with a total length of 26.054 km, Kardzhali district”

The main objective of this project proposal is the rehabilitation of road III-507 Kardzhali-Monastery from km 0+ 055 to km 26+ 109, with a length of 26.054 km. By improving and modernising the technical and operational characteristics of the road section, uniformity of the road surface will be achieved, conditions of traffic safety and comfort for travellers will be ensured. The improved conditions for crossing the road section will have a beneficial impact on the target groups of this project and the final beneficiaries — the population of Kardzhali district. The implementation of the activi…

EU budget
€6.9M
Total project cost
€8.1M
Period
2017-07-12 → 2022-10-19
Thematic objective
TO07Sustainable transport and network infrastructure

About the Sustainable transport and network infrastructure objective

Thematic Objective 7 funds sustainable transport and network infrastructure: TEN-T core-network completion, rail electrification, urban mobility, ports and inland-waterway upgrades.

Co-funding: the EU contributes €6.9M toward a total project cost of €8.1M — a co-funding rate of 85%, with the remainder covered by national, regional or private sources.

Kohesio is the European Commission's open-data platform for projects co-financed by the European Regional Development Fund, the European Social Fund Plus, the Cohesion Fund and the Just Transition Fund. It draws on lists of beneficiaries published by national managing authorities and harmonises them into a single EU-wide view.

Full project record on Kohesio — partners, deliverables, location map, related funding decisions.

Open on kohesio.ec.europa.eu →

Frequently asked questions

What is the EU budget for this project?
The EU contributes €6.9M toward a total project cost of €8.1M, a co-funding rate of 85%.
Which fund or thematic objective does it belong to?
This project falls under EU Cohesion Policy thematic objective TO07 — Sustainable transport and network infrastructure — financed through the European Structural and Investment Funds.
Which country is the project located in?
The project is located in BG.
What is the project period?
The project runs from 2017-07-12 to 2022-10-19.
Where can I find the full project record?
The complete project record — beneficiary, location and related funding decisions — is published on Kohesio, the European Commission's open-data platform, under reference Q3835746.