KOHESIO · Q3835756 · BG

Lot 19 “Road III-663 Chirpan — Simeonovgrad from km 0+ 000 to km 15+ 220, with a total length of 15.220 km, St. Zagora district”

The main result to be achieved with the implementation of the project is 15.220 km of rehabilitated road section of road III-663. With the improvement of the transport and operational qualities of the existing road section, the road safety and comfort of the travelling residents of the town of Chirpan, Zetjovo and Celina villages will be ensured, improving the state of the environment by reducing harmful greenhouse gas emissions and extending the service life of the road. Improving the quality of life and working environment of the population, attracting investment, ensuring access to educati…

EU budget
€5.0M
Total project cost
€5.9M
Period
2017-04-12 → 2020-12-07
Thematic objective
TO07Sustainable transport and network infrastructure

About the Sustainable transport and network infrastructure objective

Thematic Objective 7 funds sustainable transport and network infrastructure: TEN-T core-network completion, rail electrification, urban mobility, ports and inland-waterway upgrades.

Co-funding: the EU contributes €5.0M toward a total project cost of €5.9M — a co-funding rate of 85%, with the remainder covered by national, regional or private sources.

Kohesio is the European Commission's open-data platform for projects co-financed by the European Regional Development Fund, the European Social Fund Plus, the Cohesion Fund and the Just Transition Fund. It draws on lists of beneficiaries published by national managing authorities and harmonises them into a single EU-wide view.

Full project record on Kohesio — partners, deliverables, location map, related funding decisions.

Open on kohesio.ec.europa.eu →

Frequently asked questions

What is the EU budget for this project?
The EU contributes €5.0M toward a total project cost of €5.9M, a co-funding rate of 85%.
Which fund or thematic objective does it belong to?
This project falls under EU Cohesion Policy thematic objective TO07 — Sustainable transport and network infrastructure — financed through the European Structural and Investment Funds.
Which country is the project located in?
The project is located in BG.
What is the project period?
The project runs from 2017-04-12 to 2020-12-07.
Where can I find the full project record?
The complete project record — beneficiary, location and related funding decisions — is published on Kohesio, the European Commission's open-data platform, under reference Q3835756.